Thermalite had a production plant at Hams Hall Power Station. They used the fly ash from the power station boilers in the production process. When I worked, thermalite would deliver the blocks still steaming hot from the factory.1n the 50/60s there was a outside company down aston church rd by the cut bridge that made thermalite blocks from the old power station waste
i liked working with them becouse they was easy to cut and liftThermalite had a production plant at Hams Hall Power Station. They used the fly ash from the power station boilers in the production process. When I worked, thermalite would deliver the blocks still steaming hot from the factory.
Yes, you could cut them with a sawi liked working with them becouse they was easy to cut and lift![]()
In the link above that Pete supplied, I thought they had rebar in the roof panels. The blocks absorbed water causing the rebar to rust sag and collapse. At least that what I thought.It's easy to be confused by the different construction methods. My understanding of the problem is that it is the reinforced concrete supporting beams which are failing. Thermalite is used as non supporting blocks or slabs and has no reinforcing steel content?
It's easy to be confused by the different construction methods. My understanding of the problem is that it is the reinforced concrete supporting beams which are failing. Thermalite is used as non supporting blocks or slabs and has no reinforcing steel content?
Interesting.......I have not been involved in structural concrete; however, I have been involved with very high load flooring to support 3,000-ton presses and steel storage. Every truck load was certified material from the mixer, going back to 1976 through 2009 and we never had any issues. Currently I am involved with a project in Louisiana requiring a high pressure mix in a 25,000 sq ft building, all loads will be tested and certified.I recall that the Queensway Tunnel had a number of roof beam made from high alumina cement. Its not a bad product if made strictly to specification. The problems arose when used in certain environmental conditions like swimming pools that used chlorine or if very strict ratios of water, cement and aggregate were not adhered too. There used to be a lot of guess work when high alumina cement was first used.
The Queensway Tunnel was built in the later sixties. I cannot recall when problems with high alumina cement came to light, I seem to recall it was at a swimming’s pools roof beams, possibly at a school. The cause, and remedy was quickly identified, and programme of testing initiated.Interesting.......I have not been involved in structural concrete; however, I have been involved with very high load flooring to support 3,000-ton presses and steel storage. Every truck load was certified material from the mixer, going back to 1976 through 2009 and we never had any issues. Currently I am involved with a project in Louisiana requiring a high pressure mix in a 25,000 sq ft building, all loads will be tested and certified.
I am very surprised that the Queensway Tunnel material was not certified or possibly the specifications were not substantial.
Thanks, that it.In 1974, nine months after the Camden school roof collapse, there was the collapse at Sir John Cass in Stephen..,,
Two beams forming part of the roof over the swimming pool at the school collapsed. The investigation showed that the cause of the failure was loss of strength due to conversion of high alumina cement concrete followed by sulphate attack leading to disruption of the concrete.
This if I recall correctly is more of a problem with the design of large panel block construction than the concrete. The Ronan Point disaster sometime late 60’s was initially caused by a gas explosion, but soon proved to be poor design and construction.